To match the growing community work at Sacred Heart and improve what we can offer we have a new building project pending.
This new extension will be a place where all groups can assemble, be welcomed, learn about other services, meet other groups, where volunteers can have training, stop for a coffee and easily access HOT staff members. Here short video showing what progress is being made in our building project – Café and photos made couple days later.
HoT Capital Project Costings
Preliminaries
£8,888.00
Substructure
£59,812.77
Frame
£6,200.00
Roof
£39,470.54
External Walls
£25,000.00
Windows and External Doors
£26,000.00
Internal Walls and Partitions
£12,000.00
Internal Doors
£5,000.00
Wall Finishes
£8,500.00
Floor Finishes
£8,600.00
Ceiling Finishes
£5,000.00
Fittings and Fixtures (Office)
£10,000.00
Mechanical Installation
£6,000.00
Electrical Installation
£10,000.00
Hard & Soft Landscaping
£58,392.35
Drainage
£6,340.40
External Lighting
£3,222.38
Services
£3,300.00
Lambe extra Prelims for entire project
£9,300.00
Subtotal
£311,026.44
Larger Extension
£35,000.00
Total
£346,026.44
Contingency @ 8%
8%
£27,682.12
Total
£373,708.56
Cost Management Fees: Post Contract
1.9%
£7,100.46
VAT
20%
£74,741.71
Total Inc VAT
£456,970.82
Budget for Equipment and Fittings
Kitchen equipment, including ovens and a coffee machine
£20,000.00
Furniture including tables, chairs, serving stations etc.
£10,000.00
Food preparation, cooking utensils, crockery, glassware etc.